Memorial Avenue

  • Contractor nameInfrasource
  • Completion DateAugust 01, 2022

Agawam-West Springfield Natural Gas Pipeline Replacement Project

  • Eversource gas will be replacing 1.2 miles of gas pipeline, from the Morgan Sullivan Bridge to Union Street Extension. Work begins March of 2022 and will end in fall of 2022.
  • Click here(PDF, 539KB) for project information

Starting June 27th, Eversource Gas, through it's contractor, Infrasource, will begin the intersection and tie-over work for the 16 inch gas replacement project at the following locations:

  • Intersection of River Street & Memorial Avenue
  • Intersection of Union Street and Memorial Ave

Lane closures are required on the street, as well as the Morgan Sullivan Bridge for this work to be accomplished and will likely result in traffic delay. This work will likely continue through July 15th, but work will not be permitted on July 4th or 5th.

MassDOT Transportation Improvement Project #608374: Reconstruction of Memorial Ave from Colony Rd to the Memorial Ave Rotary

Unclaimed / Undelivered Tender of Payments for Easements

Attention: Tender of payment to some Property Owners has been unclaimed / "returned to sender" two or more times for the following properties:

  • 1146 Memorial Avenue
  • 1490 Memorial Avenue
  • 900 Memorial Avenue

Attempts to contact property owners will cease after the second attempt. Owners on record at the time of the recorded easement, who wish to collect damages awarded as part of this project, must contact the DPW at 413-263-3242 for instruction on how to accept the tender of payment.

Revised Right of Way Payment Timelines

As part of this project, it was necessary for the Town to allocate funds for just compensation in relation to the Right of Way (ROW) easement acquisition. On May 5th, 2022, the Department of Public Works distributed notices for tendering of payment to the abutters of this project impacted by the permanent or temporary easements on their property. It has come to the DPWs attention that the original payment timeline of five days within receipt of the returned form enclosed with notice will not be feasible.

Compensation checks will be mailed within 15 business days from receipt of the required W-9 Form.

The DPW thanks all involved for their understanding in this matter.


  • The Plans for Memorial Avenue Reconstruction from Colony Road to Route 5 are at 100% design level. The project is scheduled to be advertised by MassDOT as project #608374 on June 4, 2022. Actual construction would begin by 2023.
  • The estimated project value is in the $26 million range. The majority of the funding is from the MassDOT State Transportation Improvement Program. And about $2 million of the funding will be from our Water Enterprise fund for replacement of the water main from Colony Road to Union Street. (Union Street to Route 5 water main was replaced in 2003).
  • September 2021 MassDOT Approved Design Justification Workbook - click here(PDF, 3MB)
  • Current Project Schedule click here(PDF, 723KB)
  • General Construction Plans click here(PDF, 2MB).
  • Traffic Sign and Pavement Marking Plans click here(PDF, 6MB).
  • Traffic Signal Plans click here(PDF, 1MB).

Memorial Avenue and Morgan Sullivan Bridge Completed