TRAFFIC NOTICE: Morgan Road Paving Project

The Town will begin paving on Morgan Road starting Tuesday August 12th at 5:00am for a duration of approximately four (4) days, weather permitting. Please use alternate routes or travel with caution and plan for delays throughout this period.

Day 1 Morgan & Riverdale.pdf.png

Tuesday, August 12 – Start Time: 5:00 AM
Section: Riverdale to Craig

  • Westbound traffic on Morgan Road will be reduced to a single lane at Riverdale.

  • Eastbound traffic will be closed at the Morgan & Craig intersection and detoured via Pierce Street to Route 5.

  • Once paving is complete and the lanes have cooled, traffic will be shifted to the newly paved section to allow work on the final westbound lane.

 


Day 2 Morgan & Piper.pdf.png

Wednesday, August 13 – Start Time: 5:00 AM
Section: Craig to Piper

  • Westbound traffic will be permitted on Morgan Road until reaching Cayenne Street. After paving has passed the Cayenne intersection, westbound traffic will be detoured down Cayenne Street.

  • Eastbound traffic on Morgan Road will be closed at Piper Road and detoured via Piper to Amostown Road.

  • Piper Cross Road will be closed at Piper during this operation.

 


Day 3-4 Morgan & Pease.pdf.png

Thursday, August 14 & Friday, August 15 – Start Time: 5:00 AM
Section: Piper to Pease

  • Westbound traffic on Morgan Road will be closed at Piper Road and detoured via Piper to Amostown Road.

  • Eastbound traffic will remain open from Pease Road onto Morgan Road.

  • One lane will be paved each day to allow for a traffic shift onto the new pavement on Day 2.

  • All residents in the work zone will be directed to travel eastbound in alignment with the traffic flow.